01-18 2022
Production of SINOMALY in October 2021
It was the peak production season, but faced with the general rise of raw material prices and the government’s power rationing policy, the production work was once in a dilemma. However, SINOMALY quickly decided to adjust the production time, improve the staff’s production efficiency, and make full efforts to tackle key projects, roll up their sleeves and work hard. Finally, a satisfactory answer sheet was submitted. This month, the port gathering tasks such as the B03 batch of Vietnam ocean project, Suzhou SINOMALY Congo Kinshasa project and askari project of Hefei Institute were completed on time quality and quantity; Yangzhou Dingxin Uzbek project, new East transportation project, Korla project, etc. are in stable and orderly progress.
-
01-17 2022
Production of SINOMALY in September 2021
September is the last month of the third quarter. SINOMALY needs to complete the port gathering work of Hefei Cement Research and Design Institute and Nanjing Institute ocean project on time. This time, the time is tight and the task is heavy, and it is close to the National Day holiday. However, SINOMALY still perfectly completes the task with excellent professional skills, meeting the needs of customers.
-
01-14 2022
Production of SINOMALY in August 2021
On August 25, 2021, the general contractor of SINOMALY Heavy Machinery Co., Ltd. Successfully ignited the 2500 ton clinker production line per day in Uzbekistan. When this exciting news came back to China, all the staff were elated and honored, saying that they would provide better products and services for the owners with faster speed and higher quality.
-
01-14 2022
Production of SINOMALY in July 2021
In July, Liyang’s production work is in full swing. The first-line project of Uzb has been delivered to the whole line, and the second phase of the project has been steadily improved. In order to achieve the monthly production target, the production staff from top to bottom are united and concentrate on production.
-
01-14 2022
Production of SINOMALY in June 2021
In June, the production in the workshop remained at the highest point and the production capacity was fully brought into full play.Under the pressure of continuous high temperature, frequent personnel adjustment and full production, all the staff are able to face the challenge and efficient operation, and present the party’s centennial anniversary with practical actions. As a result of the repeated epidemic situation, the speed of goods going abroad slowed down and the cost increased rapidly, Uzb first-line project was once in trouble.SINOMALY is responsible for customers and project, and decides to meet customer needs regardless of cost. All the first-line products will be sent out through various channels, and gradually leave the country to complete the delivery task successfully.
-
01-14 2022
Production of SINOMALY in May 2021
The rapid rise of raw material prices has had a serious impact on the entire equipment manufacturing industry.Facing the market, SINOMALY has been working hard to reduce costs and increase efficiency, increase the circulation rate of products, fast in and fast out.
-
01-13 2022
Production of SINOMALY in April 2021
In April 2021, facing the pressure of market and delivery, the production is still stable and try its best to complete the production task.
-
10-12 2021
Production of SINOMALY in March 2021
In the first quarter of 2021, SINOMALY made a strong start of the year, perfectly completed the monthly delivery task, and achieved the feat of sending thousands of tons a day in the emergency port gathering task of Vietnam Chengsheng fourth line project and Longshan phase III project of China SINOMALY International Engineering Co., Ltd! 2021 is a year to forge ahead and open a broader market. We will build a better SINOMALY in the year of the ox!